Condo renovation Thailand rules start with a simple point: you own the inside of your unit, but the structure, the façade and the shared pipes belong to every owner in the building, so most work needs written approval from the condominium's juristic person before a contractor lifts a tool. Skip it and you risk a stop order, a lost deposit or a bill for damage to the unit below.

This guide covers approval, structural limits, permits, contracts, Phuket costs and materials. It sits alongside our wider Phuket property guide. It is general information, not legal or engineering advice; your building's registered regulations and the local authority have the final word.

Who approves condo renovation Thailand work?

Every condominium is run by a juristic person, the legal body of all co-owners, whose registered regulations and house rules govern work inside units. Our explainer on the Phuket condo juristic person shows how that body works.

In practice, most buildings ask for a written renovation application before work starts, usually with:

  • Drawings of the work, especially electrical, plumbing and air-conditioning changes.
  • The contractor's company details, worker names and ID copies for access passes.
  • A refundable damage deposit, the amount set by the building, returned after a final check of corridors and lifts.
  • A schedule that respects permitted working hours. Many buildings allow noisy work only in daytime hours from Monday to Saturday, not on Sundays or public holidays.
  • Protection for lifts and corridors and off-site debris removal.

What can you not change in a condo?

Under Section 48 of the Condominium Act B.E. 2522, letting an owner build, alter or add to their own unit at their own expense in a way that affects the common property or the external appearance of the building needs a resolution backed by at least half of all co-owners' votes. In everyday terms that covers:

  • Load-bearing walls, columns, beams and floor slabs. Cutting or removing them needs an engineer and often a permit.
  • Façade and balconies. Enclosing a balcony or changing windows, railings or outdoor unit positions alters the building's look.
  • Shared risers. Main water, drainage and electrical risers serve other units, so moving a toilet or kitchen far from existing drains may be refused.
  • Fire safety. Sprinklers, detectors and fire doors must stay working.

Ask the manager for as-built drawings showing which walls are structural.

When is a building permit needed for a house or a condo?

The Building Control Act B.E. 2522 requires anyone who intends to construct, alter or remove a building to get a licence from the local competent official, or to notify that official under Section 39 bis. The Act defines "alteration" as changing the structural elements, shape, weight or area of a building from its original condition, but excludes repairs and changes listed by ministerial regulation.

Ministerial Regulation No. 11 (B.E. 2528) lists work that does not count as alteration. In summary:

Type of workHow the regulation treats it
Replacing non-structural parts with the same or other materials that add no more than 10 percent to the load on any structural partNot an alteration
Changing floor or roof area by a combined 5 sqm or less without adding or removing columns or beamsNot an alteration
Replacing structure like for like, unless it is reinforced concrete, prestressed concrete or structural steelNot an alteration
Removing structural or reinforced concrete walls, reinforced concrete stairs or upper-floor slabsCounts as demolition unless part of exempt work

For a house, extensions, larger roofs or extra floors usually need a permit from the municipality or local administrative organisation; see our guide to building a house in Phuket. For condo renovation Thailand projects, the same test applies: new tiles, kitchens, built-ins and light partitions usually fall inside the exemptions, while heavy stone flooring, cut slabs or removed structural walls may not. Ask an engineer to check loads.

How should you hire and pay a contractor?

Get at least three itemised quotes and a bilingual written contract naming brands, dates, waste removal and liability for damage to neighbouring units. Phuket expat guides commonly suggest staged payments such as 30 percent at signing, 30 percent at a midpoint, 30 percent at practical completion and 10 percent held back for about 30 days against defects.

Unless the contract says otherwise, Section 600 of the Civil and Commercial Code makes a contractor liable for defects that appear within one year of delivery, or five years for structures on land other than wooden buildings.

On tax, a VAT-registered contractor adds VAT, currently 7 percent after the government extended the reduced rate to 30 September 2027, according to the Revenue Department and tax advisers. Ask for a full tax invoice in your name and keep it with the building's approval letter for when you sell or rent out.

What does condo renovation Thailand work cost in Phuket?

Costs depend on unit size, finish and how much plumbing moves, so treat any figure as a starting point. Phuket guides published in 2026 put a full bathroom remodel at roughly 80,000 to 250,000 baht and a kitchen at roughly 120,000 to 500,000 baht from budget to mid-range finishes, with general tradesmen at around 500 to 800 baht a day and skilled specialists more. Add a 10 to 20 percent buffer and expect jobs to overrun. These are indicative ranges, not quotes.

Which materials suit Phuket's humidity and salt air?

  • Use moisture-resistant boards and waterproof membranes behind bathroom tiles, and inspect the waterproofing before tiling.
  • Choose marine-grade stainless steel, aluminium or coated fittings near the sea; ordinary steel and chrome can rust quickly on a balcony.
  • Prefer porcelain tiles, quartz or compact laminate over raw MDF and solid timber, which can swell and attract termites.
  • Ventilate bathrooms and wardrobes to limit mould.
  • Book a licensed electrician for any new circuits, not a general builder.

For an older unit, start with a professional check of hidden problems, as described in our condo inspection Phuket guide, especially if you are buying a Phuket resale condo to refurbish.

Is renovating for rental worth it?

A refit pays only if rent covers it within a sensible period, so compare quotes with our Phuket condo rental yields guide and keep finishes durable. Check the legal side of short stays in is Airbnb legal in Phuket. Owners abroad can use a manager, as our Phuket property management guide explains.

FAQ

Does condo renovation Thailand work need permission?

Almost always from the juristic person, in writing. Work affecting the common property or exterior also needs a vote of at least half of all co-owners under Section 48.

Can I enclose my condo balcony?

Usually not without a general meeting vote, because it changes the building's external appearance, and it may also raise permit questions.

Can I remove a wall in my unit?

Light partitions often can, with approval. Structural or reinforced concrete walls need an engineer and may count as alteration or demolition under the Building Control Act.

Can a foreign owner hire a contractor directly?

Yes. Make sure contracts, receipts and tax invoices are in the owner's name, and use a registered contractor whose workers hold the right permits.

Sources: Condominium Act B.E. 2522 (Section 48); Building Control Act B.E. 2522 (Sections 4, 21, 39 bis); Ministerial Regulation No. 11 (B.E. 2528); Civil and Commercial Code Section 600; Royal Decree No. 807 on the 7 percent VAT rate; Phuket cost and payment ranges from published 2026 contractor and expat guides, reviewed in November 2026. Figures are indicative. This article is general information, not legal advice.