High-Speed Rail Project Delayed Seven Months
High-Speed Rail Project Faces Completion Setback
The highly anticipated high-speed rail project connecting Bangkok and Nong Khai has been delayed by seven months, with the completion date for the Saraburi-Kaeng Khoi section now moved from June 7 to December 25.
High-Speed Rail Project Delay Due to Structural Limitations
This extension was approved by the State Railway of Thailand (SRT) Board, citing structural limitations and the necessity to secure land-use permission from the Royal Irrigation Department as key reasons for the delay.
Structural Constraints and Land-Use Permissions Cause Delay
Land-Use Permissions Stall High-Speed Rail Progress
The SRT governor confirmed that the delay in the high-speed rail project was primarily due to the need for land-use approval from the Royal Irrigation Department, a critical step in the construction process.
SRT Board Grants Extension for High-Speed Rail Project
Despite these challenges, the SRT has delivered 100% of the required land to the contractor and is committed to expediting the remaining work to meet the new deadline.
No Additional Costs or Compensation for Delay
High-Speed Rail Project Extension Comes at No Extra Cost
The contract extension for the Saraburi-Kaeng Khoi section, which spans 12.99 kilometers and is valued at 8.56 billion baht, will not result in any additional costs or compensation claims from contractors.
Contractors Agree to Complete High-Speed Rail Within Revised Timeline
Contractors involved in the high-speed rail project have agreed to the extension without seeking extra expenses, ensuring that the SRT will not bear any additional financial burden.
Construction Timeline and Project Value
High-Speed Rail Project Construction Began in 2021
Construction of the Saraburi-Kaeng Khoi section started on February 19, 2021, and the revised completion date is now set for December 25, following the 201-day extension.
High-Speed Rail Project Section Valued at 8.56 Billion Baht
This segment of the high-speed rail project is a significant investment, reflecting the government’s commitment to enhancing Thailand’s transportation infrastructure.
Future Developments and Additional Railway Projects
SRT Proposes New Railway Crossing Bridges in Nakhon Ratchasima
In addition to the high-speed rail project delay, the SRT board has resolved to propose the construction of six new railway crossing bridges in Nakhon Ratchasima province, with a total budget of 797.29 million baht.
High-Speed Rail Project Adjustments and Future Plans
These additional infrastructure projects highlight the ongoing efforts to modernize and expand Thailand’s railway network, despite the current setbacks in the high-speed rail project.
Commitment to Timely Completion Despite Delays
SRT Vows to Expedite High-Speed Rail Construction
The SRT remains committed to completing the high-speed rail project within the revised timeframe, working closely with contractors to overcome structural and administrative challenges.
High-Speed Rail Project Remains a Priority for Thai Infrastructure
Despite the seven-month delay, the high-speed rail project continues to be a top priority, aiming to deliver improved connectivity and economic benefits upon completion.